State Route 32 Orland Complete Streets

State Route 32 Orland Complete Streets

Caltrans District 3 (D3) is proposing a Complete Streets project in Glenn County along State Route 32 (SR 32) in and near the City of Orland from Interstate 5 to County Road N. (Caltrans Project Number: 03-1N200)

Spanish / Español

Information

Project Overview

SR 32 is a two-lane conventional highway that passes through downtown Orland and includes multiple traffic signals and turn pockets.

The project proposes to implement complete street improvements along SR 32 (also known as Walker Street) through rehabilitation of existing sidewalks, new sidewalk connectivity, adding bike lanes, addressing nonstandard Americans with Disabilities Act (ADA) features, upgrading pavement and drainage systems, adding wayfinding signs, intersection improvements.


Purpose and Need

The purpose of this project is to improve complete streets infrastructure, perform intersection improvements at 9th Street and Tehama Street, and improve drainage systems.

Complete street features along this route, such as sidewalks, have deteriorated and have connectivity gaps. There is a lack of existing infrastructure for additional modes of active transportation, such as bicycling or walking. Existing ADA curb ramps are not compliant with the latest standard. Drainage systems in the area have deteriorated due to age and will require rehabilitation or replacement to restore functionality. Additionally, the City of Orland has identified multiple locations around the downtown area that experiences frequent flooding and excessive gutter flow. The existing pavement is cracking and deterioration. The city has indicated a need for intersection improvements to calm traffic exiting the freeway.


Local Agency Outreach

The City of Orland shared the Walker Street Master Plan with Caltrans that showcases the city's vision for Downtown Orland. In collaboration with the City of Orland, Glenn County Active Transportation Plan, and Caltrans' assessment of needs on SR 32, Caltrans is working closely to ensure the project aligns with those goals and community needs.


Funding

Caltrans will be seeking 2028 State Highway Operation and Protection Program (SHOPP) funding for the remaining phases of the project and is subject to California Transportation Commission (CTC) approval. The CTC is responsible for programming and allocating funds for the construction of highways, passenger rail, transit and active transportation improvements throughout California. 


Map

State Route 32 project map

Project Timeline

complete
complete

Project Initiation

November 6, 2024: Caltrans met with local agencies to review proposed project

April 23, 2025: Finalized the Project Initiation Report (PIR) 

Spring 2028: target schedule for CTC to vote and approve to begin project development

planned
planned

Project Approval and Environmental Document

Summer 2028: target schedule to begin PA&ED phase 

Winter/Spring 2030: target schedule to finalize PA&ED phase

During this phase, Caltrans will conduct environmental studies, prepare the environmental document, technical analysis, and approval of the project design concept. 

planned
planned

Final Project Design

Spring 2030 - Fall 2031: target schedule to finalize design plans

Winter 2032 - Spring 2032: target schedule advertise and award contract to contractor

During this phase, Caltrans will complete project design, prepare engineering plans, and construction specifications. Any necessary right-of-way coordination or utility adjustments will occur in parallel with final project design. Caltrans will coordinate with federal, state, and local agencies to secure all required environmental permits and approvals. 

planned
planned

Construction

Summer 2032 - Summer 2034: target construction schedule