State Route 20 & Humphrey Road - Safety Improvement

State Route 20 & Humphrey Road - Safety Improvement

Caltrans District 3 is proposing a safety improvement project at the State Route 20 (SR 20) and Humphrey Road intersection near Yuba City in Sutter County. The goal of the project is to create a safer intersection for motorists. (Caltrans Project Number 03-4J060/SHOPP ID 25854)

Information

Background

SR 20 is a major east-west transportation corridor through Sutter County, connecting local communities with the greater Yuba-Sutter region and providing access to Interstate 5 to the west in Colusa County and SR 99 and SR 70 to the east. The route serves a diverse mix of local, commuter, agricultural and commercial traffic.

The intersection of SR 20 and Humphrey Road is located west of Yuba City in a predominantly rural and agricultural area. Humphrey Road provides local access to nearby residence, and agricultural properties, resulting in vehicles entering, exiting and crossing SR 20.

As traffic and transportation needs along the corridor continue to evolve, Caltrans is evaluating improvements at the SR 20 and Humphrey Road intersection to enhance safety and provide a more effective intersection configuration for motorists.


Project Overview

The project will evaluate the condition of the intersection, design and construct intersection improvements such as a roundabout or traffic signal.


Need

The intersection reported a total of 13 collisions over a 5-year period (January 1, 2017, to December 31, 2021), involving six injuries and one serious injury. Collision types included broadside that were caused by a failure to yield, sideswipe, and rear-ended. The Humphrey Road minor street approaches are offset from one another, which creates inefficient signal phasing issues at the intersection as well as more conflict points than a conventional intersection. Existing vegetation at the intersection creates sight distance limitations. 

Purpose 

The purpose of this project is to improve safety for motorists at the intersection and to reduce the number of injury collisions that have occurred at the current two-way stop-controlled intersection.


Funding

This project was approved at the August 2023 California Transportation Commission (CTC) meeting to begin project development and is funded by the State Highway Operation and Protection Program (SHOPP). The CTC is responsible for programming and allocating funds for the construction of highway, passenger rail, transit and active transportation improvements throughout California. 

Total Project Cost Estimate: $14,380,000


Local Agency Outreach

Caltrans is working with Sutter County throughout the project development process. 


Map

Map of State Route 20 & Humphrey Road project


Photo

Photo of State Route 20 & Humphrey Road intersection

Project Timeline

complete
complete

Project Initiation

June 23, 2023: Caltrans finalized the Project Initiation Report (PIR) 

August 17, 2023: Safety project voted and approved at CTC meeting to begin project development 

live
live

Project Approval and Environmental Document

August 2023: PA&ED phase officially started

November 20, 2024: Caltrans met with Sutter County to inform them about the project

March 5, 2025: Public Open House and survey at Sutter High School 

Spring 2027: target schedule to finalize PA&ED


During this phase, Caltrans:

  • performs technical analysis
  • completes required environmental studies
  • identifies potential impacts and avoidance, minimization, and/or mitigation
  • prepares and approves both the DED and the Final Environmental Document
  • finalizes the project design concept

planned
planned

Draft Environmental Document (DED) and Public Review

Fall 2026: target schedule to release DED for public review and comment

Fall 2026: 30-day public comment period (dates TBD)

Fall 2026: Public Open House (location TBD) 

Purpose of this stage is to gather formal public comments on environmental analysis and alternatives.

planned
planned

Final Project Design

Fall 2027 - Fall 2028: target schedule to finalize design plans

Fall 2028 - Spring 2029: target schedule advertise and award contract to contractor

During this phase, Caltrans will complete project design, prepare engineering plans, and construction specifications. Any necessary right-of-way coordination or utility adjustments will occur in parallel with final project design. Caltrans will coordinate with federal, state, and local agencies to secure all required environmental permits and approvals. 

 

planned
planned

Construction

Spring 2029 - Fall 2029: target construction schedule