Overview:

[Insert any additional information of what the environmental phase will include specific to this project prior to the official release of the Draft Environmental Document, if there is one.]

 

Map:Map of the project area

 

Schedule:  

  • Preliminary Planning: 2012-2021
  • Environmental: 2024-2029
  • Public review that will inform the Environmental Impact Report/Environmental Impact Studies (EIR/EIS) scheduled for spring of 2025.
  • Environmental Impact Report/Environmental Impact Studies (EIR/EIS) expected to be complete by 2029.
  • Design 2029-2034 
  • Construction 2034-2038 (pending funding)

Your Voice Matters!

Caltrans wants to hear from you! Your feedback will help us understand the needs of the people who use and live near this corridor. 

Just click the blue "Continue" button at the bottom of this page or the "Participate" tab at the top of this page. 

Caltrans makes every attempt to ensure our documents are accessible. Due to variances between assistive technologies, there may be portions of documents which are not accessible. Where documents cannot be made accessible, we are committed to providing alternative access to the content. Should you need additional assistance, please contact us at (916) 654-2852 or visit https://dot.ca.gov/request-ada-compliant-documents.