Kern Kings Complete Street Project

Kern Kings Complete Street Project

This project proposes to address Bicycle and Pedestrian Infrastructure by building 10,090 feet of sidewalk, 27 curb ramps, 73 driveways and 2,500 feet of additional bike lane. Location 1 is within Kettleman City on State Route (SR) 41 from PM 17.93 to PM 18.35. Location 2 is within the City of Buttonwillow on SR 58 from PM 26.72 to PM 28.2.

 

 

Information

Project Overview

Project consists of the following proposed improvements:

  • Construction of 10,090 linear feet of sidewalk to provide continuous and reliable pedestrian pathways.
  • Installation of 27 curb ramps to improve accessibility for individuals with mobility challenges and ensure compliance with accessibility standards.
  • Development of 73 driveways to facilitate safe entry and exit for vehicles and pedestrians.
  • Addition of 2,500 linear feet of bike lanes to encourage cycling and enhance safety for cyclists.

These targeted improvements represent a strategic investment in active transportation. By advancing the quality and accessibility of infrastructure, the project seeks to foster a safer and more inclusive environment for all members of the community, supporting healthier and more sustainable modes of travel.

Purpose:

The purpose of this project is to provide a pedestrian and bicyclists active transportation infrastructure and bring the facility into compliance with Federal, State, and Departmental standards for accessibility.

 

Need:

This complete street project is needed to mitigate the lack of active transportation facilities for pedestrians and bicyclists traveling within the underserved communities of Kettleman, and Buttonwillow.

Project Map: 

Location 1Location 2

 

Funding and Cost: 

Funding Source: SHOPP Complete Streets

Cost: The escalated construction capital is $5,900,000 and the total escalated Right of Way capital outlay cost is $507,000.

Funding Year: 2033/2034

 

Your Voice Matters!

Caltrans wants to hear from you! Your feedback will help us understand the needs of the people who use and live near this corridor. 


To leave a voicemail comment, call 855 925 2801, project code: 10944

To send an email comment: b76448@publicinput.com

Project Timeline

complete
complete

Project Initiation

Project Initiation Document was completed in June 2025

planned
planned

Supplemental PIR

Supplemental PIR is scheduled for completion in October 2026

planned
planned

Project Approval and Environmental Document

March 2027

planned
planned

Project Design

September 2029

planned
planned

Construction

2032